Downtown Loveland Traffic Signal Replacement Project

What work is being done? 

CDOT will begin work on traffic signal improvements at the following six intersections in Loveland:

•         N Lincoln Avenue (northbound US 287) at E 5th Street

•         N Lincoln Avenue (northbound US 287) at E 6th Street

•         N Lincoln Avenue (northbound US 287) at E 7th Street

•         Cleveland Avenue (southbound US 287) at E 5th Street

•         Cleveland Avenue (southbound US 287) at E 6th Street

•         Cleveland Avenue (southbound US 287) at E 7th Street

 

Crews will remove the existing outdated traffic signals and install new devices. Enhancements include upgrades to traffic and pedestrian signals, closed-circuit television cameras (CCTV) for traffic surveillance, and fiber optic cable and communications systems improvements.

Why is the work being completed? 

The project will improve traffic flow and enhance pedestrian safety at the crosswalks.

 

When will crews be working?

Activities will begin on Monday, March 2, at the intersection of Cleveland Ave and 7th St, with the project moving south towards 5th St. Once work is completed on Cleveland Ave, construction will shift to Lincoln Ave and 5th St and continue northbound. The working hours are from 7 a.m. to 4 p.m., Monday to Friday.

 

Travel Impacts 

During activities, motorists may experience lane restrictions and a speed limit reduction at the intersections. However, one lane of traffic will remain open at all times. Activities may require temporary sidewalk closures with pedestrian detours in place.

Email: signalreplacementinloveland@gmail.com

Website: https://www.codot.gov/projects/signal-replacement-project-in-loveland